Current Projects

[ Progress Chart | Current Projects |  Completed Projects | Future Projects ]

Current Projects


A status update of each current project is provided below. Every capital project requires approval from the Ministry of Infrastructure before it is ready for construction. 
?
As projects proceed and circumstances become better clarified, the dates below are subject to change. 

This page is updated monthly following each Board Meeting. 
istockblprnt-2191423134.840a68208072.jpg


Kwantlen Park Secondary Addition (Site 048)

  • Address: 
  • Project Type: Addition, 20 classrooms
  • Approval: Ministry of Education and Child Care approval January 10, 2023
  • Current Phase: Construction 35%
  • Construction Contract: Olivit Construction Ltd.
  • Target Occupancy: September 2027

Guildford Park Secondary Addition (Site 047)

  • Address: 
  • Project Type: Addition, 14 classrooms
  • Approval: Ministry of Education and Child Care approval May 26, 2023
  • Current Phase: Construction 23%
  • Construction Management Services: Unitech Construction Management Ltd.
  • Target Occupancy: June 2028

Tamanawis Secondary Addition (Site 150)

  • Address: 
  • Project Type: Addition, 23 classrooms
  • Approval: Ministry of Education and Child Care approval May 9, 2023
  • Current Phase: Construction 38%
  • Construction Contract: D.G.S. Construction Company Ltd.
  • Target Occupancy: September 2027

Old Yale Road Elementary Prefab Addition (Site 064)

  • Address: 
  • Project Type: Pre-fabricated Modular Addition, 10 classrooms + 7 More (17 total)
  • Approval: Ministry of Education and Child Care approval May 16, 2024 for 10 classrooms; July 5, 2024 for additional 7 classrooms
  • Current Phase: Construction 60%
  • Construction Management Services: Heatherbrae Builders Co. Ltd.
  • Target Occupancy: January 2027

Martha Currie Elementary Prefab Addition (Site 061)

  • Address: 
  • Project: Pre-fabricated Modular Addition, 6 classrooms
  • Approval: Ministry of Education and Child Care approval May 16, 2024
  • Current Phase: Construction 47%
  • Construction Management Services: Unitech Construction Management Ltd.
  • Target Occupancy: October 2026

Latimer Road Elementary Prefab Addition (Site 035)

  • Address: 
  • Project Type: Prefabricated Modular Addition, 6 classrooms
  • Approval: Ministry of Education and Child Care approval July 5, 2024
  • Current Phase: Construction 75%
  • Construction Management Services: Heatherbrae Builders Co. Ltd.
  • Target Occupancy: September 2026

William Watson Elementary Prefab Addition (Site 057)

  • Address: 
  • Project Type: Prefabricated Modular Addition, 12 classrooms
  • Approval: Ministry of Education and Child Care approval July 5, 2024
  • Current Phase: Construction 27%
  • Construction Management Services: Unitech Construction Management Ltd.
  • Target Occupancy: November 2026

George Greenaway Elementary Prefab Addition (Site 090)

  • Address: 
  • Project Type: Addition, 14 classrooms
  • Approval: Ministry of Education and Child Care approval September 9, 2024
  • Current Phase: Construction 43%
  • Construction Management Services: Unitech Construction Management Ltd.
  • Target Occupancy: January 2027

Forsyth Road Elementary Addition (Site 183)

  • Address: 
  • Project Type: Addition, 14 classrooms
  • Approval: Ministry of Education and Child Care approval June 10, 2024
  • Current Phase: Construction 0%
  • Construction Management Services: Pro-Can Construction Group Corp.
  • Target Occupancy: Fall 2028

Fleetwood Park Secondary Addition (Site 167)

  • Address: 
  • Project Type: Addition, 32 classrooms
  • Approval: Ministry of Education and Child Care approval June 27, 2024
  • Current Phase: Design
  • Tender: Fall 2026
  • Target Occupancy: Spring 2029

Clayton Heights Secondary Addition (Site 175)

  • Address: 
  • Project Type: Addition, 41 classrooms
  • Approval: Ministry of Infrastructure approval July 4, 2025
  • Current Phase: Design
  • Tender: Summer 2027
  • Target Occupancy: Fall 2029

Grandview Heights Secondary Addition (Site 177)

  • Address: 
  • Project Type: Addition, 20 classrooms
  • Approval: Ministry of Infrastructure approval February 10, 2026
  • Current Phase: Design
  • Tender: Spring 2027
  • Target Occupancy: Fall 2029

Redwood Park New Elementary School (Site 214)

  • Address: 17320 and 17390 20 Avenue area
  • Project Type: New School, 37 classrooms
  • Approval: Awaiting funding from Ministry of Infrastructure
  • Current Phase: Planning, Business Case
  • Tender: Pending Ministry of Infrastructure funding approval
  • Target Occupancy: Pending Ministry of Infrastructure funding approval